What is the most effective way for a Construction Quality Manager to use KPIs to...

What is the most effective way for a Construction Quality Manager to use KPIs to evaluate the impact of improvements implemented in a construction project?

A.

Tracking as many KPIs as possible to gather extensive data.

B.

Focusing on cost-related KPIs as they are the most concrete indicators of success.

C.

Selecting KPIs that directly reflect the goals of the implemented improvements.

D.

Evaluating KPIs at the end of the project to see the final impact.