During the closeout phase of a construction project, the client requests a comprehensive set of...

During the closeout phase of a construction project, the client requests a comprehensive set of quality records, including all modifications, inspections, and change orders that occurred throughout the project. The quality manager is responsible for ensuring the accuracy and accessibility of all documentation for final submission.

Which of the following actions should the construction quality manager take when submitting the final set of documents?

A.

Include all documentation submitted by subcontractors as received.

B.

Submit the planned documents, trusting that all changes were properly recorded and verified by the project team throughout the construction process.

C.

Review each document for alignment with the latest project changes and ensure approval by relevant authorities.

D.

Prioritize submitting documents that highlight positive project outcomes.

CCQM PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CCQM pdf
Get 75% Discount on All Products, Use Coupon: "ac75sure"