You have been hired as the cost engineer for a mechanical contractor and have been...

You have been hired as the cost engineer for a mechanical contractor and have been provided the following information:

What is the schedule performance index (SPI)?

A.

ACWP/BCWS= 110,000/100,000= 1.10

B.

BCWS/ACWP = 100,000/110,000 = 0.91

C.

BCWP/BCWS = 105,000/100,000- 1.05

D.

BCWS/BCWP= 100,000/105,000-0.95