You are reporting the following Earned Value Analysis information for the project:EV= $1,500,000AC=$1.

You are reporting the following Earned Value Analysis information for the project:

EV= $1,500,000

AC=$1.000,000

PV= $2,000,000

What is the status of the project?

A.

Project is ahead of schedule, but over budget

B.

Project is behind schedule, but over budget

C.

Project is behind schedule, but under budget

D.

Project is ahead of schedule, but under budget