When using a fixed-price.

When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?

A.

For changes in prices calculated in accordance with a methodology proposed by the contractor at tender stage.

B.

For changes in construction cost 'or varied works carried out beyond the original dale of completion

C.

In no situation

D.

For changes in The cost of resources beyond the control of either party