After collecting the control information on a light rail project within an original budget of...

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the schedule variance (SV)?

A.

BCWS - BCWP = 100.000 – 105,000 = -5,000

B.

ACWP - BCWS = 110.000 – 100,000 = 10,000

C.

BCWS -ACWP = 100.000 – 110,000 - -10,000

D.

BCWP - BCWS = 105.000 - 100.000 =- 5,000

CCP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CCP pdf
Get 75% Discount on All Products, Use Coupon: "ac75sure"