After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the cost variance (CV)?

A.

BCWP-ACWP = 105,000-110,000 = -5,000

B.

ACWP-BCWP = 110,000-105,000 = 5,000

C.

BCWS-ACWP = 100,000-110,000 = -10,000

D.

ACWP-BCWS = 110,000-100,000 = -10,000