A credit card organization currently has multiple related change initiatives.

A credit card organization currently has multiple related change initiatives. The second initiative is taking longer than expected due to delayed access to subject matter expertise in a particular area. Which portion of the change management plan for the delayed initiative is directly impacted by this subject matter expertise requirement?

A.

Learning and development plan

B.

Risk mitigation plan

C.

Resource plan

D.

Sustainability plan