FIDIC CCM Question Answer
You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?