You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow...

You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?

A.

The Contractor submits a Value Engineering proposal regarding the lighting system for the operation rooms. The Engineer is positive about the proposal and tells the Contractor they need to look into it.

B.

The Engineer instructs a change in slopes of the access road to the intensive care unit to meet the Employer's Requirement. The Engineer does so with a Notice in accordance with Sub-Clause 3.5.

C.

The Engineer requests a proposal regarding a change in type of windows and doors. The Contractor submitted the proposal accordingly to the Engineer. The Engineer instructs the Variation.

D.

The Employer verbally instructs a change in the type of doors. The Engineer issued a Notice describing the required change and denying any costs for the Contractor.

CCM PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CCM pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"