Through which two of the following documents may the Employer give information to the Contractor of a planned timetable of meetings such as management meetings, site meetings, technical meetings, and progress meetings?

Choose all of the correct answers (multiple possibilities).

A.

General Conditions of Contract

B.

Specification

C.

Special Conditions

D.

Employer's Requirements