For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?

A.

After issuance of the Taking-Over Certificate.

B.

After issuance of the Performance Certificate.

C.

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.

Until all outstanding works as stated in the Taking-Over Certificate are completed.