(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the...

(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the Contractor allowed to start the design of the Works before the Commencement Date? (1 correct answer applies))

A.

Yes, but Contractor will do so on its own risk.

B.

Yes, Contractor can start design and execution of the Works to make sure it won ' t lose any time.

C.

No, because any design or execution before the Commencement Date is prohibited in Clause 8.

D.

Yes, but Contractor will do so on Employer ' s risk.