A new regulation results in organizations needing to change online contractual wording.

A new regulation results in organizations needing to change online contractual wording. A business analyst (BA) has elicited the requirements and documented them in a change control request. Where will the BA find out which stakeholder has the authority to approve, deny, or defer the change request?

A.

Information management

B.

Business analysis approach

C.

Governance approach

D.

Stakeholder engagement approach