Why is a risk assessment usually conducted after a Business Impact Analysis (BIA) as part...

Why is a risk assessment usually conducted after a Business Impact Analysis (BIA) as part of the analysis stage?

A.

Conducting a BIA ties up personnel on this project; so resources are not available to conduct the risk assessment until after personnel are released from the BIA project

B.

Conducting the risk assessment after the BIA has identified priorities enables the risk assessment to maximise investment in risk treatments where they are most needed

C.

A risk assessment is not required until Business Continuity solutions based on the outcomes of the BIA have been developed for review

D.

Risk assessments are not required until after the organization's business plan has been updated to confirm any changes in plans as a result of the BIA

CBCI PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CBCI pdf
Get 80% Discount on All Products, Use Coupon: "BFDEAL80"