You are creating the solution scope for an identified problem in your organization.

You are creating the solution scope for an identified problem in your organization. You are working with several stakeholders during this process including the domain subject matter expert, the implementation subject matter expert, the project manager, and the sponsor.

Which of these stakeholders will be responsible for writing the project scope?

A.

Domain subject matter expert

B.

Business analyst

C.

Project manager

D.

Sponsor