It is a document that records all change requests for the project.
B.
It is a document that tracks all unauthorized changes to the project solution.
C.
It is a document that tracks all characteristics and status of changes that have been received.
D.
It is a document that tracks the changes that have been received, including their implementation to the project solution.
The Answer Is:
C
This question includes an explanation.
Explanation:
A change log is a tool that helps to manage and monitor the changes that affect the requirements, the solution, or the project. A change log tracks all characteristics and status of changes that have been received, such as the source, description, priority, impact, approval, and resolution of the changes. A change log can help to ensure that the changes are properly documented, communicated, and controlled, and that they are aligned with the stakeholder needs and expectations. References: BABOK Guide v3, page 54; CBAP / CCBA Certified Business Analysis Study Guide, page 161.
CBAP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"