Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

Henry is the business analyst for his organization.

Henry is the business analyst for his organization. Management has created a pre-determined budget of

$450,000 for his solution. Henry has identified the project requirements but now wants to prioritize them based on timeboxing and budgeting. Henry examines the cost of the requirements and begins removing the requirements from the allowed list in order to meet the $450,000 budget.

What timeboxing or budgeting approach is Henry using?

A.

Parametric

B.

All in

C.

Selective

D.

All out

CBAP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CBAP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"