Which of the following is the formal acceptance of the project?
A.
A project review
B.
A sign-off
C.
Risk assessment
D.
Inspection trend analysis
The Answer Is:
B
This question includes an explanation.
Explanation:
A sign-off is the formal acceptance of the project by the stakeholders, indicating that they agree that the project has met the requirements and delivered the expected value. A project review is an evaluation of the project performance and outcomes, but it does not necessarily imply acceptance. Risk assessment is a process of identifying and analyzing potential threats and opportunities that may affect the project. Inspection trend analysis is a technique of monitoring the quality of the project deliverables by comparing the results of inspections over time. References:
CBAP / CCBA Certified Business Analysis Study Guide, 2nd Edition, Chapter 10, page 367
BABOK® Guide, Section 7.6, page 294
CBAP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"