Which of the following defines the deliverable the customer is expecting?
A.
Project charter
B.
Procurement management plan
C.
Product scope statement
D.
Project network diagram
The Answer Is:
C
This question includes an explanation.
Explanation:
The product scope statement defines the deliverable the customer is expecting. It describes the features, functions, and characteristics of the product, service, or result that will be produced by the project. It also defines the acceptance criteria, assumptions, and constraints related to the product scope. The product scope statement is a key input for developing the project scope statement, which defines the work that needs to be done to deliver the product scope. The product scope statement is usually created by the business analyst in collaboration with the customer and other stakeholders, and approved by the solution owner. References: IIBA BABOK Guide v3, section 5.1.2, page 162; CBAP / CCBA Certified Business Analysis Study Guide, chapter 6, page 233; Free CBAP CBAP® Exam Questions - IIBA CBAP Exam - Study4Exam, question 242.
CBAP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"