When can the Product Backlog be updated? (Choose the best answer)
A.
Only after a Sprint Review if agreed to by the stakeholders
B.
Only during Product Backlog refinement sessions if the Product Owner is present
C.
Never, unless agreed to by the change request
D.
At any time when done by the Product Owner or at the Product Owner’s discretion
The Answer Is:
D
This question includes an explanation.
Explanation:
The Product Backlog is under the Product Owner’s control and can be updated anytime. TheScrum Guidestates: "The Product Owner is accountable for effective Product Backlog management," implying ongoing adjustments as needed.
A:Limiting updates to Sprint Review contradicts its emergent nature.
B:Refinement is a key activity, but updates aren’t restricted to it.