PMI CAPM Question Answer
Why is tailoring in a project necessary?
Requirements keep changing.
An artifact must be produced.
A tool or technique is required.
Each project is unique.
Each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide.
TESTED 30 Jan 2026
Copyright © 2014-2026 ACE4Sure. All Rights Reserved