Who identifies project requirements in the early phase of the project?
A.
Business analyst, product team, and key stakeholders
B.
Project manager, business analyst, and key stakeholders
C.
Project manager, business analyst, and project sponsor
D.
Project sponsor, business analyst, and key stakeholders
The Answer Is:
B
This question includes an explanation.
Explanation:
In the Initiating and early Planning phases of a project, the identification of requirements is a collaborative effort. While the Business Analyst (BA) often leads the elicitation, they do not work in a vacuum.
Why Choice B is correct:
The Business Analyst: Responsible for the " what. " They use elicitation techniques (interviews, focus groups, surveys) to draw out the requirements from those who will use or be affected by the solution.
The Project Manager: Responsible for the " how " and " when. " The PM ensures that requirements align with the project charter and constraints (budget, time, and resources). They manage the process of capturing these requirements to build the Scope Statement.
Key Stakeholders: These are the primary sources of requirements. Stakeholders include end-users, department heads, and subject matter experts (SMEs). Without their input, the requirements would be incomplete or inaccurate.
The Synergy: The PM and BA work together to ensure that the requirements provided by the stakeholders are clear, measurable, and achievable within the project ' s boundaries.
Analysis of other options:
A (Product team): While the product/development team may provide technical constraints later, they are typically not the primary " identifiers " of business requirements in the early phases. They consume the requirements to build the solution.
C and D (Focusing on the Sponsor): While the Project Sponsor provides the high-level business case and project objectives (the " why " ), they are usually not involved in the granular identification of requirements. They delegate this to the stakeholders who will actually use the product. Choice B is more comprehensive by including the " Key Stakeholders " group, which covers a much broader and more accurate range of requirement sources.
Key Concept: The Project Management Institute (PMI) emphasizes that " Requirement Identification " is a foundational step in Scope Management. By involving the Project Manager, Business Analyst, and Key Stakeholders (Choice B), the organization ensures that the project has a balanced view of technical feasibility, business value, and user needs, which is documented in the Requirements Documentation and the Requirements Traceability Matrix (RTM).
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"