Which project performance domain is the work breakdown structure (WBS) developed?
A.
Development approach and life cycle
B.
Delivery performance
C.
Project work
D.
Planning
The Answer Is:
D
This question includes an explanation.
Explanation:
The PMBOKĀ® Guide (7th Edition) introduced eight Project Performance Domains, which are groups of related activities that are critical for the effective delivery of project outcomes.
Why Choice D is correct:
Defining the Work: The Planning Performance Domain involves the initial, ongoing, and evolving coordination required to deliver the project ' s products and outcomes.
Scope Breakdown: Creating the Work Breakdown Structure (WBS) is a foundational planning activity. It involves organizing and defining the total scope of the project.
Baseline Creation: The WBS is a key component of the Scope Baseline (along with the WBS Dictionary and the Project Scope Statement). You cannot accurately plan for cost, schedule, or resources without first decomposing the work into manageable work packages via the WBS.
Iterative Nature: Planning is not a one-time event; as the project progresses and more information becomes available, the WBS may be refined within this domain.
Analysis of other options:
A (Development approach and life cycle): This domain focuses on determining whether the project will use a Predictive, Adaptive, or Hybrid approach and defining the phases of the project. While this decision influences how you build the WBS, it is not the domain where the WBS itself is developed.
B (Delivery performance): This domain focuses on delivering the scope and quality that the project was undertaken to achieve. It is about the result of the work and meeting requirements, rather than the structural planning of the work.
C (Project work): This domain is associated with managing the physical and logistical aspects of the project, such as managing resources, maintaining a productive environment, and managing the flow of work. It is more about the " execution " and " monitoring " of the work rather than the hierarchical decomposition of the scope.
Key Concept: The Project Management Institute (PMI) emphasizes that the Planning Performance Domain (Choice D) is where the project team establishes the roadmap. The WBS is the structural skeleton of that roadmap, ensuring that every piece of work is accounted for so that budgets and schedules can be built with precision.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"