Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
A.
Organizational process updates
B.
Quality metrics
C.
Change requests
D.
Quality control measurements
The Answer Is:
B
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide (Project Quality Management), specifically within the Plan Quality Management process, Quality Metrics are a key output. A quality metric specifically describes a project or product attribute and how the Control Quality process will measure it.
Output of Plan Quality Management: During the planning phase, the team identifies which quality standards are relevant to the project and determines how to satisfy them. The specific, measurable thresholds (e.g., percentage of tasks completed on time, failure rate, number of defects identified per day) are documented as Quality Metrics.
Input to Manage Quality (Perform Quality Assurance): The process of Manage Quality (often referred to as Quality Assurance) uses these metrics as a basis for auditing the quality requirements and the results from quality control measurements. It ensures that the project is using appropriate quality standards and operational definitions to meet the stakeholder ' s expectations.
Examples of Metrics: These can include reliability, availability, test coverage, number of bugs per line of code, or customer satisfaction scores.
Analysis of Distractors:
A. Organizational process updates: While these can be an output of various processes (including Manage Quality), they are not the primary functional input used to perform quality assurance audits.
C. Change requests: These are typically an output of the Manage Quality or Control Quality processes when variations are found that require corrective action.
D. Quality control measurements: These are an output of Control Quality and an input to Manage Quality. While they are an input to the assurance process, they are not an output of Plan Quality Management (which is a planning process, not an execution/control process).
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"