Which item is an input to the Define Activities process?
A.
Schedule data
B.
Activity list
C.
Risk register
D.
Scope baseline
The Answer Is:
D
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, specifically within the Project Schedule Management knowledge area, the Define Activities process is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Scope Baseline: This is a primary input to the Define Activities process. The scope baseline consists of the Project Scope Statement, the Work Breakdown Structure (WBS), and the WBS Dictionary. Since the goal of Define Activities is to break down work packages into specific activities, the project manager must start with the WBS (found within the scope baseline) to ensure all required work is accounted for.
The Breakdown Process: In the hierarchy of project planning, you first define the scope, then decompose that scope into work packages (Create WBS), and finally decompose those work packages into activities (Define Activities). Therefore, the baseline containing those work packages is a mandatory starting point.
Why the other options are incorrect:
A. Schedule data: This is an output of the Develop Schedule process. It includes items such as schedule milestones, activity attributes, and documentation of assumptions and constraints. It is created much later in the planning sequence.
B. Activity list: This is the primary output of the Define Activities process itself. It is the comprehensive list of all schedule activities required to be performed on the project.
C. Risk register: While risks can influence activity durations or resource requirements, the Risk Register is not a standard formal input for the initial identification of activities in the Define Activities process. It becomes more relevant during Estimate Activity Durations and Develop Schedule.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"