Which enterprise environmental factors may influence Plan Schedule Management?
A.
Cultural views regarding time schedules and professional and ethical behaviors
B.
Historical information and change control procedures
C.
Risk control procedures and the probability and impact matrix
D.
Resource availability and organizational culture and structure
The Answer Is:
D
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, specifically the Plan Schedule Management process, Enterprise Environmental Factors (EEFs) refer to conditions, not under the control of the project team, that influence, constrain, or direct the project.
Impact on Schedule Planning: When developing the Schedule Management Plan, the project manager must consider the environment in which the project operates. Key EEFs include:
Organizational culture and structure: This affects how schedules are developed and managed (e.g., a highly bureaucratic culture may require more formal approval levels).
Resource availability: The availability of physical and human resources directly dictates how a schedule can be constructed and whether certain activities can run in parallel.
Project management software: The specific tools provided by the organization for scheduling.
Commercial databases: Resource leveling or standardized duration estimates from industry databases.
Comparison with other options:
A. Cultural views... and ethical behaviors: While " culture " is an EEF, the specific phrasing regarding " professional and ethical behaviors " is more aligned with the Code of Ethics and Professional Conduct rather than the primary environmental inputs listed in the PMBOKĀ® Guide for Schedule Management.
B. Historical information and change control procedures: These are classified as Organizational Process Assets (OPAs), not EEFs. OPAs are internal to the organization (like templates and past project files), whereas EEFs are the environment/conditions surrounding the project.
C. Risk control procedures and the probability and impact matrix: These are also Organizational Process Assets (OPAs) typically found in the Risk Management Plan or the organization ' s process library, used to guide how risk is handled rather than the environmental factors influencing the schedule ' s creation.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"