Which actions should a project manager follow to manage stakeholders?
A.
Identify the key stakeholders and keep them informed at all times.
B.
Identify the stakeholders, planning, managing and monitoring their engagement
C.
Meet and keep informed any person related to the project, at all times
D.
Identify the stakeholders and monitor their level of satisfaction
The Answer Is:
B
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, specifically the Project Stakeholder Management knowledge area, managing stakeholders involves a structured four-step process aimed at ensuring the right people are involved in the right way throughout the project lifecycle.
Identify, Planning, Managing, and Monitoring (Choice B): This choice directly maps to the four formal processes defined in the PMI standards:
Identify Stakeholders: Identifying the people, groups, or organizations that could impact or be impacted by the project.
Plan Stakeholder Engagement: Developing approaches to involve stakeholders based on their needs, expectations, interests, and potential impact.
Manage Stakeholder Engagement: Communicating and working with stakeholders to meet their needs/expectations and foster appropriate engagement.
Monitor Stakeholder Engagement: Monitoring project stakeholder relationships and tailoring strategies for engaging stakeholders through the modification of engagement strategies and plans.
Identify and Keep Informed (Choice A): While communication is a part of stakeholder management, " keeping them informed at all times " is neither practical nor efficient. Stakeholder management requires a tailored strategy based on an interest/power grid, not just constant information.
Meet and Keep Informed any Person (Choice C): This is incorrect because it is impossible and counterproductive to keep every person related to a project informed " at all times. " Project managers must prioritize stakeholders based on their level of influence and impact.
Identify and Monitor Satisfaction (Choice D): While monitoring satisfaction is important, this choice skips the critical steps of Planning and Managing the engagement, which are active processes required to reach that satisfaction.
Effective Project Stakeholder Management focuses on continuous communication with stakeholders to understand their needs and expectations, addressing issues as they occur, and managing conflicting interests to ensure project success.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"