When cost variance is negative and schedule variance is positive, the project is:

When cost variance is negative and schedule variance is positive, the project is:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.