When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what...

When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what should the practitioner do first?

A.

Develop the feature as a parallel work package.

B.

Shorten the current work period and begin the new work.

C.

Ask a dedicated team member to complete it immediately.

D.

Prioritize it in the requirements list for the next work period.