What tern describes an intentional activity to modify a nonconforming product or product component?
A.
Preventive action
B.
Corrective action
C.
Defect repair
D.
Updates
The Answer Is:
C
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, specifically within the Direct and Manage Project Work and Control Quality processes, there are four types of change requests. The term for modifying a nonconforming product is Defect Repair.
Defect Repair: This is an intentional activity to modify a nonconforming product or product component. It is reactive in nature and focuses on fixing a specific deliverable that does not meet the established quality requirements or standards.
Analysis of other options:
A. Preventive action: This is an intentional activity that ensures the future performance of the project work is aligned with the project management plan. It is proactive and aimed at preventing a problem before it occurs.
B. Corrective action: This is an intentional activity that realigns the performance of the project work with the project management plan. While similar to defect repair, corrective action typically refers to the process or the project performance (e.g., getting back on schedule), whereas defect repair refers specifically to the product or deliverable.
D. Updates: These are changes to formally controlled project documents, plans, etc., to reflect modified or additional ideas or content.
Per PMI standards, defect repair is a key output of the quality control process and is performed to bring a specific component back into compliance with requirements.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"