What process is included in Project Schedule Management?
A.
Estimate Activity Durations
B.
Create Work Breakdown Structure (WBS)
C.
Direct and Manage Project Work
D.
Estimate Activity Resources
The Answer Is:
B
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide (6th Edition), Project Schedule Management includes the processes required to manage the timely completion of the project. There are six specific processes within this Knowledge Area:
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Durations
Develop Schedule
Control Schedule
Estimate Activity Durations is the process of estimating the number of work periods needed to complete individual activities with estimated resources. This process is critical for developing the overall project schedule.
Analysis of Distractors:
B (Create Work Breakdown Structure): This is a process within the Project Scope Management knowledge area. While the WBS provides the " framework " for the schedule, the act of creating it is fundamentally about defining the scope of work.
C (Direct and Manage Project Work): This is an executing process within the Project Integration Management knowledge area. It involves leading and performing the work defined in the project management plan.
D (Estimate Activity Resources): In the PMBOKĀ® Guide 6th Edition, this process was moved to the Project Resource Management knowledge area. While resources heavily influence duration, the process itself is categorized under Resource Management because it focuses on the " what " and " who " rather than the " how long. "
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"