What is the schedule performance index (SPI) if the planned value (PV) is $100, the...

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

A.

0.50

B.

0.67

C.

1.50

D.

2.00