According to the PMBOKĀ® Guide (6th Edition) and the Standard for Project Management, the very first process in the Project Stakeholder Management knowledge area is Identify Stakeholders.
This process occurs in the Initiating Process Group, often starting as soon as the Project Charter is approved (or even while it is being developed). The logical flow of stakeholder management dictates that you must know who is involved before you can plan how to engage them.
The key steps in the Project Stakeholder Management Knowledge Area are:
Identify Stakeholders: Identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project.
Plan Stakeholder Engagement: Developing approaches to involve stakeholders based on their needs, interests, and potential impact.
Manage Stakeholder Engagement: Communicating and working with stakeholders to meet their needs and address issues.
Monitor Stakeholder Engagement: Monitoring project stakeholder relationships and tailoring strategies for engaging stakeholders.

Analysis of Distractors:
A (Plan Stakeholder Engagement): This is the second step. You cannot create an engagement plan until you have a Stakeholder Register (the output of Identify Stakeholders) listing who needs to be engaged.
C (Manage Stakeholder Responsibility): This is not a formal PMI process name. While a project manager manages engagement and clarifies roles (often via a RACI chart), " Manage Stakeholder Responsibility " is not a defined step in the PMBOKĀ® Guide.
D (Monitor Stakeholder Activity): This is part of the final, ongoing process (Monitor Stakeholder Engagement) that occurs during the Monitoring and Controlling phase, not at the beginning of the project.