What earned value (EV) measure indicates the cost efficiency of the work completed?
A.
Cost variance (CV)
B.
Cost performance index (CPI)
C.
To-complete performance index (TCPI)
D.
Variance at completion (VAC)
The Answer Is:
B
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, specifically in the Control Costs process within the Project Cost Management knowledge area, the Cost Performance Index (CPI) is the specific metric used to measure the cost efficiency of a project.
Definition of CPI: CPI is a measure of the cost efficiency of budgeted resources, expressed as the ratio of earned value ($EV$) to actual cost ($AC$). The formula is:
$$CPI = \frac{EV}{AC}$$
Efficiency Indicator: Because it is an index (a ratio), it tells you how much value you are getting for every dollar spent.
A CPI of 1.0 indicates the project is exactly on budget (spending $1 to get $1 of work).
A CPI greater than 1.0 indicates that the work is being performed with better efficiency than planned (under budget).
A CPI less than 1.0 indicates that the work is being performed inefficiently (over budget).
Importance: CPI is considered the most critical EVM metric as it influences the calculation of the Estimate at Completion (EAC). It provides a clear snapshot of how efficiently the project team is using the financial resources allocated to the project.
Why other options are incorrect:
Option A: Cost variance (CV): While CV also relates to cost performance, it is expressed as a currency value ($CV = EV - AC$) rather than a ratio. It shows the magnitude of the deviation from the budget, but not the " efficiency rate " or " percentage " of efficiency.
Option C: To-complete performance index (TCPI): TCPI is a measure of the cost performance that must be achieved with the remaining resources to meet a specific goal (like the original BAC or a new EAC). It describes the efficiency required for the future, not the efficiency of the work already completed.
Option D: Variance at completion (VAC): VAC is a projection of the final budget deficit or surplus ($VAC = BAC - EAC$). It is a forecasting metric used to see where the project will end up, not a measure of current work efficiency.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"