What document gathers all of the lessons learned at the end of a phase or project
A.
Lessons learned register
B.
Lessons learned list
C.
Lessons learned project asset
D.
Lessons learned repository
The Answer Is:
A
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, the Lessons Learned Register is the primary project document used to record knowledge gained during a project or a phase. This document is created early in the project and is updated throughout the lifecycle as an output of the Manage Project Knowledge process.
The distinction between the choices depends on the timing and the specific document type as defined by PMI:
Lessons Learned Register (Choice A): This is a project document used to record challenges, risks, opportunities, or other content that can be used to improve performance in the current project or future phases. At the end of a project or phase, the information in this register is transferred to the Lessons Learned Repository.
Lessons Learned Repository (Choice D): This is part of the Organizational Process Assets (OPAs). While the repository is where the information is eventually stored for the entire organization ' s long-term use, the specific document that " gathers " and captures these details during the execution and at the conclusion of a project phase is the register.
Choices B and C: These are not standard PMI terms. While " lessons learned " may be referred to as assets or lists informally, they are not formal project management documents recognized in the PMBOKĀ® Guide.
In the Close Project or Phase process, the Lessons Learned Register is finalized and its contents are archived into the Lessons Learned Repository to support continuous improvement across the organization.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"