What are the project management processes associated with project quantity management?
A.
Plan Quality Management, Manage Quality, and Control Quality
B.
Plan Quality Management, Manage Quality, and Cost of Quality
C.
Manage Quality, Customer Satisfaction, and Control Quality
D.
Customer Satisfaction, Control Quality, and Continuous Improvement
The Answer Is:
A
This question includes an explanation.
Explanation:
According to the PMBOK® Guide, specifically the Project Quality Management knowledge area, there are three formal processes designed to ensure that the project meets the needs for which it was undertaken. (Note: The user ' s question mentions " Quantity, " but in the context of PMI certification and the provided choices, this is a known typo for Quality Management).
The Three Formal Processes (Choice A):
Plan Quality Management: The process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements.
Manage Quality: Sometimes called " Quality Assurance, " this is the process of translating the quality management plan into executable quality activities that incorporate the organization’s quality policies into the project. It focuses on the processes used to create the deliverables.
Control Quality: The process of monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. It focuses on the deliverables themselves.
Cost of Quality (Choice B): This is a Tool and Technique used within the Plan Quality Management process, not a standalone process itself.
Customer Satisfaction (Choice C and D): This is a fundamental principle or objective of quality management, but it is not a named process in the PMI framework.
Continuous Improvement (Choice D): This (also known as kaizen) is an organizational philosophy or an outcome of effective quality management, but it is not one of the three specific processes defined in the PMBOK® Guide.
By following these three processes, a project manager ensures that the " Triple Constraint " is maintained and that the final product adheres to the scope and functional requirements defined by the stakeholders.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"