PMI CAPM Question Answer
Which type of estimating is used to improve the accuracy of an activity's duration?
Analogous
Parametric
Three-point
What-if scenario analysis
TESTED 15 Sep 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved