What is the purpose of an adaptive standup meeting?
To review what work has been completed, remove impediments, and calculate velocity
To ask the team what work has been completed, calculate velocity, and determine what work will be completed
To ask the team what work has been completed, ask what work will be completed, and report impediments
To update the burndown chart, calculate velocity, and report impediments