The project manager has following information about duration for an activity:

* Most likely [tM] - 15 days

* Pessimistic [tP] - 20 days

* Optimistic [tO] - 10 days

What is the estimated duration of this activity, according to the triangular distribution technique?

A.

10 days

B.

15 days

C.

12.5 days

D.

5 days