The milestone list is an input to which process from the Planning Process Group?
A.
Define Activities
B.
Estimate Activity Durations
C.
Estimate Activity Resources
D.
Sequence Activities
The Answer Is:
D
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, the Milestone List is a primary input to the Sequence Activities process within the Project Schedule Management knowledge area.
Process Relationship: While the Milestone List is created as an output of the Define Activities process, it must then be funneled into Sequence Activities to ensure that these significant points or events are logically linked to the activities that lead up to them or follow them.
Definition of a Milestone: A milestone is a significant point or event in a project. It has zero duration because it represents a moment in time rather than work being performed.
The Logic of Sequencing: When building a Project Schedule Network Diagram, the project manager must sequence not just the work packages and activities, but also the milestones (such as " Design Approved " or " Contract Signed " ). This ensures that the schedule model reflects the true logical flow of the project, including these critical constraints or achievement markers.
Comparison with Other Options:
Define Activities (A): This is the process that produces the Milestone List as an output. An output of a process cannot be an input to the same process in the standard linear planning flow.
Estimate Activity Durations (B): This process focuses on the amount of time needed to complete individual activities. Since milestones have zero duration, the milestone list is not a primary driver for estimating the time required for work.
Estimate Activity Resources (C): This process identifies the types and quantities of resources (people, equipment, materials) required. Milestones do not consume resources themselves; they are markers of progress.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"