PMI CAPM Question Answer
The following is a network diagram for a project.
What is the critical path for the project?
A-B-C-F-G-I
A-B-C-F-H-I
A-D-E-F-G-I
A-D-E-F-H-I
TESTED 06 Jul 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved