The correct equation for schedule variance (SV) is earned value:

The correct equation for schedule variance (SV) is earned value:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].