Which of the following schedule network analysis techniques is applied when a critical path method...

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management