Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses