One of the outputs of the project schedule is a detailed plan.

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

A.

It represents how and when the project will deliver the products, services, and results defined in the project scope

B.

It creates a formal record of the project and shows the organizational commitment to the project

C.

It describes how the scope will be defined, developed, monitored, controlled and validated

D.

It provides the needs of a stakeholder or stakeholder group