PMI CAPM Question Answer
Which input to the Plan Risk Management process provides information on high-level risks?
Project charter
Enterprise environmental factors
Stakeholder register
Organizational process assets
TESTED 06 Jul 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved