In project management, a temporary project can be:
A.
Completed without planning
B.
A routine business process
C.
Long in duration
D.
Ongoing to produce goods
The Answer Is:
C
This question includes an explanation.
Explanation:
According to the PMBOK® Guide (Project Management Body of Knowledge), the fundamental definition of a project is a temporary endeavor undertaken to create a unique product, service, or result. PMI clarifies the term " temporary " in the following ways:
Long in Duration (Option C): While a project is " temporary " (meaning it has a defined beginning and end), this does not mean it must be short. A project can last for several years (e.g., building a skyscraper or developing a new aircraft) and still be classified as temporary because it will eventually reach its conclusion.
Routine Business Process (Option B) / Ongoing (Option D): These options describe Operations. Operations are ongoing and repetitive (e.g., a manufacturing line or accounting services), whereas projects are unique and end when their objectives have been met or the project is terminated.
Completed without Planning (Option A): This contradicts all PMI standards. Every project requires a degree of planning (whether predictive/waterfall or adaptive/agile) to ensure that resources are used efficiently and objectives are met.
In the PMI framework, the temporary nature of a project indicates that the project team is disbanded and resources are reassigned once the project’s specific goals are achieved, regardless of how many years the project took to complete.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"