In an agile and adaptive project, which scope management entity invokes stakeholder engagement?
A.
Collect Requirements
B.
Create work breakdown structure (WBS)
C.
Plan Scope Management
D.
Scope Baseline
The Answer Is:
A
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide and the Agile Practice Guide, the Collect Requirements process is the primary bridge between the project team and the stakeholders regarding the project ' s scope.
Active Engagement: This process is inherently collaborative. It requires the project manager and team to use interpersonal and team skills (such as facilitation, observation, and conflict management) and data gathering techniques (interviews, focus groups, and workshops) to draw out stakeholder needs.
Agile Context: In an agile/adaptive environment, this engagement is continuous. Rather than a single event at the beginning of the project, requirements are collected and refined throughout the project via backlogs and frequent reviews. The Stakeholder Engagement is invoked because the team cannot define the " Definition of Ready " or " Definition of Done " without direct, ongoing input from the stakeholders.
Requirements Traceability: By engaging stakeholders here, the project manager ensures that the requirements reflect actual business needs, which are then documented in the Requirements Traceability Matrix (RTM) or the Product Backlog.
Analysis of Other Options:
B. Create work breakdown structure (WBS): While stakeholders might review a WBS, the actual creation is a technical decomposition process performed by the project team. The initial " invocation " of engagement happens during the identification of the requirements that populate the WBS.
C. Plan Scope Management: This is a planning process that creates the manual for how scope will be handled. It defines the processes, but the active, hands-on engagement with the broader stakeholder group occurs during the collection of the requirements themselves.
D. Scope Baseline: This is an output (comprising the Scope Statement, WBS, and WBS Dictionary). It is a static document/approval point, not a process that " invokes " engagement.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"