How is the schedule variance calculated using the earned value technique?
A.
EV less AC
B.
AC less PV
C.
EV less PV
D.
AC less EV
The Answer Is:
C
This question includes an explanation.
Explanation:
In accordance with the PMBOKĀ® Guide and the standard practices for Earned Value Management (EVM), Schedule Variance (SV) is a measure of schedule performance expressed as the difference between the earned value and the planned value.
The Formula:
$$SV = EV - PV$$
EV (Earned Value): The measure of work performed expressed in terms of the budget authorized for that work.
PV (Planned Value): The authorized budget assigned to scheduled work.
Interpretation of Results:
Positive SV ($ > 0$): Indicates that the project is ahead of schedule (more work has been earned than was planned).
Negative SV ($ < 0$): Indicates that the project is behind schedule (less work has been earned than was planned).
Zero SV ($= 0$): Indicates that the project is exactly on schedule.
Comparison with Other Options:
EV less AC (A): This is the formula for Cost Variance (CV) ($CV = EV - AC$). It measures cost performance.
AC less PV (B): This is not a standard EVM metric used for performance measurement.
AC less EV (D): This is essentially the inverse of Cost Variance and is not a standard project management formula.
In the Control Schedule process, SV is a critical indicator used to determine if the project is deviating from the schedule baseline and if corrective or preventive actions are required.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"